Special Plan BRGF Project

   The Special Plan (BRGF) funded works under distribution system of NBPDCL are in 3 packages :
  • Package A – BRGF Phase –I (Strengthening,Improvement and Augmentation of distribution system under BRGF Scheme) in all 21 Districts.
  • Package B – BRGF Phase –II & Balance work of Phase-I (Strengthening of distribution system & Removal of Distribution constraints) in 04 districts(Siwan, Purnea, Araria and Kishanganj).
  • Package C – Strengthening of Distribution Network in Bihar under special Plan (BRGF) Phase-II, Balance work of Phase-I for 17 districts and Phase-II Part-C for all 21 districts of North Bihar under Special Plan(BRGF Schemes).
Work/ Scheme

BRGF Phase I
BRGF Phase II
BRGF Phase II Part C
RE Works
Cost (INR) Cr.

935.27
1484.1
271.49
337.72

   Physical progress of project as on October’19 :

                        BRGF Phase-I
            New PSS: 12 Nos
            Augmentation of Power Transmformers from 5MVA to 10 MVA:64 Nos
            R&M of PSS: 179 Nos
            New 33 KV Lines: 639.1 CKM
            New 11 KV Lines: 1249 CKM
            Augmentation/Installation of additional Transformer: 1128 No Completed
            New LT Lines: 1350 CKM
            R&M of DSS: 7084 Nos
            District Control Rooms: 19 Nos
            System and Consumer Metering: Completed
            Extension of Control Rooms: 77 Nos.
                        BRGF Phase-II
            New PSS - 20 Nos
            New 33 KV Lines: 1142.6 CKM
            R&M of 33 KV Lines: 194 CKM
            New 11 KV Lines: 3251.9 CKM
            R&M of 11 KV Lines: 2468 CKM
            New LT Lines: 7321 CKM
            R&M of LT Lines: 2145 CKM
            New DSS: 3915 Nos
            R&M of DSS: 9454 Nos
            Augmentation of DSS: 934.5 nos
            New Sub-division Control Rooms: 64 Nos
                        BRGF Phase-II Part C
            R&M of 11 KV Lines: 112.72 CKM
            R&M of LT Lines: 3318 CKM